Action Date | Action Description |
---|---|
Nov 20, 2007 | Assent Application Received |
Nov 21, 2007 | Administrative Review for Completeness |
Nov 21, 2007 | Team Review for Completeness |
Nov 21, 2007 | Team Review for Completeness |
Nov 21, 2007 | Application Accepted |
Nov 21, 2007 | Deficiency - Phone Call to Applicant/Owner |
Nov 27, 2007 | Plans Received |
Dec 14, 2007 | HPHC Historical Preservation No Effect |
Jan 15, 2008 | Additional Information Requested from Applicant |
Feb 11, 2008 | Correspondence Received |
Apr 01, 2008 | Plans Received |
May 05, 2008 | Additional Information Received |
May 06, 2008 | Typist for Processing |
May 06, 2008 | Executive Sign Off |
May 06, 2008 | Sent to Photo Copy |
May 06, 2008 | Permit Approved |
May 06, 2008 | Biologist Report |
May 06, 2008 | Engineering Report |
May 29, 2008 | Land Evidence Date |