Action Date | Action Description |
---|---|
Nov 30, 2007 | Assent Application Received |
Dec 03, 2007 | Administrative Review for Completeness |
Dec 05, 2007 | Team Review for Completeness |
Dec 05, 2007 | Team Review for Completeness |
Dec 05, 2007 | Application Accepted |
Jan 03, 2008 | HPHC Historical Preservation No Effect |
Feb 15, 2008 | Typist for Processing |
Feb 15, 2008 | Sent to Photo Copy |
Feb 15, 2008 | Permit Approved |
Feb 15, 2008 | Engineering Report |
Mar 05, 2008 | Land Evidence Date |
Sep 29, 2008 | Commencement of Work Notice received |