Action Date | Action Description |
---|---|
Jan 04, 2008 | Assent Application Received |
Jan 07, 2008 | Administrative Review for Completeness |
Jan 09, 2008 | Team Review for Completeness |
Jan 09, 2008 | Team Review for Completeness |
Jan 09, 2008 | Application Accepted |
Feb 14, 2008 | HPHC Historical Preservation No Effect |
Apr 03, 2008 | Biologist Report |
Apr 03, 2008 | Engineering Report |
Apr 07, 2008 | Typist for Processing |
Apr 07, 2008 | Executive Sign Off |
Apr 07, 2008 | Sent to Photo Copy |
Apr 07, 2008 | Permit Approved |
May 01, 2008 | Land Evidence Date |
Jun 11, 2013 | Extension Toll letter mailed |
Mar 13, 2014 | Modification Request |
Mar 14, 2014 | Administrative Review for Completeness |
Mar 26, 2014 | Team Review for Completeness |
Mar 26, 2014 | Deficient Application - Owner Notification Sent |
Dec 03, 2015 | Deficient Application Discarded/No deficiency Reponse |