Action Date | Action Description |
---|---|
Jul 28, 2009 | Assent Application Received |
Jul 28, 2009 | Administrative Review for Completeness |
Jul 29, 2009 | Team Review for Completeness |
Jul 29, 2009 | Application Accepted |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Apr 07, 2010 | Correspondence Received |
Apr 08, 2010 | Correspondence Mailed/Faxed/E-mailed |
Jan 23, 2013 | Permit Approved |
Jan 23, 2013 | Engineering Report |
Jan 23, 2013 | Typist for Processing |
Jan 23, 2013 | Biologist Report |
Jan 24, 2013 | Executive Sign Off |
Jan 24, 2013 | Sent to Photo Copy |
Feb 21, 2013 | Land Evidence Date |
May 27, 2015 | Modification Request |
Jun 01, 2015 | Administrative Review for Completeness |