Action Date | Action Description |
---|---|
Sep 11, 2009 | Assent Application Received |
Sep 11, 2009 | Administrative Review for Completeness |
Sep 18, 2009 | Team Review for Completeness |
Sep 18, 2009 | Team Review for Completeness |
Sep 18, 2009 | Application Accepted |
Nov 09, 2009 | Public Notice End Date |
May 27, 2010 | Correspondence Received |
Jun 18, 2010 | Additional Information Received |
Aug 18, 2010 | Engineering Report |
Aug 20, 2010 | Biologist Report |
Aug 26, 2010 | Executive Signoff of Staff Reports |
Aug 31, 2010 | Ready to Schedule Semi-Monthly Meeting |
Sep 01, 2010 | Mail Agenda Notice |
Sep 28, 2010 | Semi-Monthly Meeting Date Scheduled |
Oct 06, 2010 | Mail Agenda Notice |
Oct 12, 2010 | Council Approval Granted |
Oct 12, 2010 | Semi-Monthly Meeting Held |
Oct 13, 2010 | Semi-Monthly Meeting Date Scheduled |
Oct 26, 2010 | Legal Response/Decision |
Nov 08, 2010 | Water Quality Certification |
Nov 22, 2010 | Stipulation Package from Biologist |
Nov 22, 2010 | Stipulation Package by Engineer |
Dec 02, 2010 | Typist for Processing |
Dec 02, 2010 | Permit Approved |
Dec 03, 2010 | Executive Sign Off |
Dec 03, 2010 | Sent to Photo Copy |
Jan 05, 2011 | Correspondence Received |
Jan 13, 2012 | Commencement of Work Notice received |
Jun 28, 2012 | Site Inspection |