Action Date | Action Description |
---|---|
Sep 15, 2009 | Assent Application Received |
Sep 16, 2009 | Administrative Review for Completeness |
Sep 18, 2009 | Team Review for Completeness |
Sep 18, 2009 | Application Accepted |
Sep 28, 2009 | 30 day Public Notice Issued |
Oct 09, 2009 | HPHC Historical Preservation No Effect |
Oct 22, 2009 | 30 day Public Notice Issued |
Oct 26, 2009 | Public Notice End Date |
Nov 19, 2009 | Objections/Comments Received |
Nov 22, 2009 | Public Notice End Date |
Dec 22, 2009 | Biologist Report |
Dec 22, 2009 | Engineering Report |
Dec 22, 2009 | Executive Signoff of Staff Reports |
Dec 23, 2009 | Additional Information Received |
Dec 30, 2009 | Ready to Schedule Semi-Monthly Meeting |
Dec 30, 2009 | Mail Agenda Notice |
Jan 13, 2010 | Council Approval Granted |
Jan 13, 2010 | Semi-Monthly Meeting Date Scheduled |
Jan 26, 2010 | Stipulation Package from Biologist |
Jan 26, 2010 | Stipulation Package by Engineer |
Jan 29, 2010 | Permit Approved |
Feb 03, 2010 | Land Evidence Date |
Feb 18, 2010 | Legal Response/Decision |
Sep 15, 2010 | Modification Request |
Sep 17, 2010 | Administrative Review for Completeness |
Sep 17, 2010 | Team Review for Completeness |
Sep 22, 2010 | Modification Approved |
Sep 23, 2010 | Team Review for Completeness |
Sep 24, 2010 | Typist for Processing |
Sep 24, 2010 | Executive Sign Off |
Sep 24, 2010 | Sent to Photo Copy |
Jan 18, 2011 | Duplicate Original Assent requested/mailed |
Jan 19, 2011 | Land Evidence Date |
Apr 04, 2012 | Correspondence Received |
Dec 04, 2012 | Extension Toll letter mailed |