Action Date | Action Description |
---|---|
Dec 09, 2009 | Buffer Zone Management Application Received |
Dec 10, 2009 | Administrative Review for Completeness |
Dec 11, 2009 | Team Review for Completeness |
Dec 11, 2009 | Application Accepted |
Dec 15, 2009 | Biologist Report |
Dec 15, 2009 | Typist for Processing |
Dec 15, 2009 | Executive Sign Off |
Dec 15, 2009 | Sent to Photo Copy |
Dec 17, 2009 | HPHC Historical Preservation No Effect |
Dec 23, 2009 | Land Evidence Date |
May 11, 2010 | Correspondence Received |
May 17, 2010 | Letter of Authorization |