Action Date | Action Description |
---|---|
Aug 09, 2011 | Freshwater Wetland - Preliminary Determination |
Aug 10, 2011 | Administrative Review for Completeness |
Aug 15, 2011 | Team Review for Completeness |
Aug 15, 2011 | Application Accepted |
Aug 19, 2011 | Biologist Report |
Aug 19, 2011 | Engineering Report |
Aug 22, 2011 | Typist for Processing |
Aug 22, 2011 | Permit Approved |
Aug 25, 2011 | Executive Sign Off |
Aug 25, 2011 | Sent to Photo Copy |
Sep 01, 2011 | Land Evidence Date |
Sep 14, 2011 | Water Quality Certification |
Sep 20, 2011 | HPHC Historical Preservation No Effect |
Dec 07, 2011 | Commencement of Work Notice received |