Action Date Action Description
Aug 10, 2011 Assent Application Received
Aug 11, 2011 Administrative Review for Completeness
Aug 15, 2011 Team Review for Completeness
Aug 15, 2011 Team Review for Completeness
Aug 15, 2011 Application Accepted
Aug 22, 2011 30 day Public Notice Issued
Aug 25, 2011 HPHC Historical Preservation No Effect
Aug 31, 2011 Category B assigned
Sep 22, 2011 Public Notice End Date
Oct 10, 2011 HPHC Historical Preservation No Effect
Oct 25, 2011 Engineering Report
Nov 08, 2011 Council Approval Granted
Nov 08, 2011 Semi-Monthly Meeting Held
Nov 08, 2011 Semi-Monthly Meeting Date Scheduled
Nov 10, 2011 US Army Corps of Engineers Approval Received
Nov 28, 2011 Stipulation Package from Biologist
Nov 28, 2011 Stipulation Package by Engineer
Nov 28, 2011 Biologist Report
Dec 16, 2011 Legal Response/Decision
Dec 21, 2011 Typist for Processing
Dec 21, 2011 Permit Approved
Dec 22, 2011 Executive Sign Off
Dec 22, 2011 Sent to Photo Copy
Jan 25, 2012 Land Evidence Date
Feb 23, 2012 Water Quality Certification
Sep 04, 2012 Additional Information Received
Oct 03, 2012 Monitoring Report
Dec 10, 2012 Correspondence Received
Dec 19, 2013 Monitoring Report
Dec 19, 2013 Monitoring Report
Jan 06, 2015 Monitoring Report
Apr 23, 2015 Monitoring Report
Jan 04, 2016 Monitoring Report
Dec 19, 2016 Monitoring Report
Jan 08, 2018 Monitoring Report
Dec 13, 2019 Monitoring Report
Dec 28, 2020 Monitoring Report
Jan 28, 2022 Monitoring Report

Details:

File No
2011-08-031
Town
East Providence
First Name
Narragansett Bay Commission
Last Name
Street
Campbell Avenue
Location
102 Campbell Avenue
Plat/Map
302
Lot/Block
01
Decision Date
Dec 21, 2011
Dock Reg.No
Project
Improvements to man made levees @ Bucklin Point
Description
Sewage Treatment Facilities (& Alteratio
Water Area
Easement
0
Acceptance Date
Aug 15, 2011

Back to List