Action Date | Action Description |
---|---|
Sep 20, 2011 | Assent Application Received |
Sep 20, 2011 | Administrative Review for Completeness |
Sep 21, 2011 | Team Review for Completeness |
Sep 21, 2011 | Team Review for Completeness |
Sep 21, 2011 | Application Accepted |
Sep 21, 2011 | Biologist Report |
Sep 22, 2011 | Engineering Report |
Sep 26, 2011 | Typist for Processing |
Sep 26, 2011 | Permit Approved |
Sep 27, 2011 | Executive Sign Off |
Sep 27, 2011 | Sent to Photo Copy |
Oct 04, 2011 | Land Evidence Date |
Oct 20, 2011 | Commencement of Work Notice received |
Nov 15, 2011 | HPHC Historical Preservation No Effect |