Action Date | Action Description |
---|---|
Sep 28, 2011 | Assent Application Received |
Oct 03, 2011 | Administrative Review for Completeness |
Oct 03, 2011 | Team Review for Completeness |
Oct 03, 2011 | Team Review for Completeness |
Oct 03, 2011 | Additional Information Received |
Oct 03, 2011 | Application Accepted |
Oct 29, 2011 | HPHC Historical Preservation No Effect |
Dec 21, 2011 | Additional Information Received |
Dec 23, 2011 | Additional Information Received |
Dec 29, 2011 | Biologist Report |
Dec 30, 2011 | Engineering Report |
Jan 05, 2012 | Typist for Processing |
Jan 05, 2012 | Permit Approved |
Jan 06, 2012 | Executive Sign Off |
Jan 06, 2012 | Sent to Photo Copy |
Feb 03, 2012 | Land Evidence Date |