Action Date | Action Description |
---|---|
Dec 13, 2011 | Assent Application Received |
Dec 14, 2011 | Administrative Review for Completeness |
Dec 14, 2011 | Team Review for Completeness |
Dec 14, 2011 | Team Review for Completeness |
Dec 14, 2011 | Application Accepted |
Dec 22, 2011 | HPHC Historical Preservation No Effect |
Jan 13, 2012 | Biologist Report |
Jan 13, 2012 | Engineering Report |
Jan 17, 2012 | Typist for Processing |
Jan 17, 2012 | Permit Approved |
Jan 19, 2012 | Executive Sign Off |
Jan 19, 2012 | Sent to Photo Copy |
May 09, 2012 | Water Quality Certification |
Jul 26, 2013 | Land Evidence Date |