Action Date | Action Description |
---|---|
Feb 08, 2012 | Maintenance Certification Request |
Feb 08, 2012 | Administrative Review for Completeness |
Feb 10, 2012 | Team Review for Completeness |
Feb 10, 2012 | Team Review for Completeness |
Feb 10, 2012 | Deficient Application - Owner Notification Sent |
Feb 29, 2012 | Deficient Application Picked Up |
Mar 23, 2012 | Deficiency Response Received |
Mar 27, 2012 | Team Review for Completeness |
Mar 27, 2012 | Team Review for Completeness |
Mar 27, 2012 | Application Accepted |
Mar 30, 2012 | 30 day Public Notice Issued |
Apr 22, 2012 | HPHC Historical Preservation No Effect |
Apr 30, 2012 | Public Notice End Date |
May 11, 2012 | Biologist Report |
May 11, 2012 | Engineering Report |
May 15, 2012 | Permit Approved |
May 15, 2012 | Category B assigned |
May 15, 2012 | Typist for Processing |
May 16, 2012 | Executive Sign Off |
May 16, 2012 | Sent to Photo Copy |
May 22, 2012 | Land Evidence Date |