Action Date | Action Description |
---|---|
Feb 22, 2012 | Assent Application Received |
Feb 23, 2012 | Administrative Review for Completeness |
Feb 24, 2012 | Team Review for Completeness |
Feb 24, 2012 | Team Review for Completeness |
Feb 24, 2012 | Application Accepted |
Mar 06, 2012 | 30 day Public Notice Issued |
Mar 22, 2012 | Objections/Comments Received |
Apr 03, 2012 | HPHC Historical Preservation No Effect |
Apr 06, 2012 | Public Notice End Date |
May 09, 2012 | US Army Corps of Engineers Approval Received |
Aug 16, 2012 | Additional Information Received |
Sep 10, 2012 | Correspondence Received |
Nov 01, 2012 | Additional Information Received |
Jan 15, 2013 | Supervisor Biologist SignOff |
Jan 15, 2013 | Supervisor Engineer SignOff |
Jan 15, 2013 | Biologist Report |
Jan 15, 2013 | Engineering Report |
Jan 16, 2013 | Executive Signoff of Staff Reports |
Mar 14, 2013 | Ready to Schedule Semi-Monthly Meeting |
Mar 14, 2013 | Mail Agenda Notice |
Mar 26, 2013 | Semi-Monthly Meeting Date Scheduled |
Mar 29, 2013 | Category A* (Docks) |
Apr 01, 2013 | Typist for Processing |
Apr 02, 2013 | Executive Sign Off |
Apr 02, 2013 | Sent to Photo Copy |
Apr 02, 2013 | Permit Approved |
Apr 15, 2013 | Land Evidence Date |
May 02, 2013 | Legal Response/Decision |