Action Date | Action Description |
---|---|
Mar 08, 2012 | Assent Application Received |
Mar 09, 2012 | Administrative Review for Completeness |
Mar 09, 2012 | Team Review for Completeness |
Mar 09, 2012 | Team Review for Completeness |
Mar 09, 2012 | Application Accepted |
Mar 14, 2012 | 30 day Public Notice Issued |
Apr 04, 2012 | Plans Received |
Apr 14, 2012 | Public Notice End Date |
Apr 22, 2012 | HPHC Historical Preservation No Effect |
May 08, 2012 | Biologist Report |
May 08, 2012 | Engineering Report |
May 09, 2012 | Category A* (Docks) |
May 09, 2012 | Typist for Processing |
May 09, 2012 | Executive Sign Off |
May 09, 2012 | Sent to Photo Copy |
May 09, 2012 | Permit Approved |
May 14, 2012 | US Army Corps of Engineers Approval Received |
Jul 27, 2012 | Land Evidence Date |