Action Date | Action Description |
---|---|
Jul 10, 2012 | Assent Application Received |
Jul 10, 2012 | Administrative Review for Completeness |
Jul 16, 2012 | Team Review for Completeness |
Jul 16, 2012 | Team Review for Completeness |
Jul 16, 2012 | Application Accepted |
Jul 17, 2012 | 30 day Public Notice Issued |
Aug 17, 2012 | Public Notice End Date |
Sep 01, 2012 | HPHC Historical Preservation No Effect |
Sep 28, 2012 | Additional Information Received |
Oct 01, 2012 | Executive Signoff of Staff Reports |
Oct 01, 2012 | Ready to Schedule Semi-Monthly Meeting |
Oct 01, 2012 | Biologist Report |
Oct 01, 2012 | Engineering Report |
Oct 01, 2012 | Mail Agenda Notice |
Oct 09, 2012 | Council Approval Granted |
Oct 09, 2012 | Semi-Monthly Meeting Held |
Oct 09, 2012 | Semi-Monthly Meeting Date Scheduled |
Oct 15, 2012 | Stipulation Package from Biologist |
Oct 15, 2012 | Stipulation Package by Engineer |
Oct 15, 2012 | Legal Response/Decision |
Oct 16, 2012 | Typist for Processing |
Oct 16, 2012 | Executive Sign Off |
Oct 16, 2012 | Sent to Photo Copy |
Oct 16, 2012 | Permit Approved |
Oct 22, 2012 | US Army Corps of Engineers Approval Received |
Oct 25, 2012 | Land Evidence Date |