Action Date | Action Description |
---|---|
Aug 31, 2012 | Assent Application Received |
Sep 04, 2012 | Administrative Review for Completeness |
Sep 04, 2012 | Team Review for Completeness |
Sep 04, 2012 | Team Review for Completeness |
Sep 04, 2012 | Application Accepted |
Sep 17, 2012 | HPHC Historical Preservation No Effect |
Oct 09, 2012 | Additional Information Received |
Dec 12, 2012 | Biologist Report |
Dec 12, 2012 | Engineering Report |
Dec 14, 2012 | Typist for Processing |
Dec 14, 2012 | Executive Sign Off |
Dec 14, 2012 | Sent to Photo Copy |
Dec 14, 2012 | Permit Approved |
Dec 28, 2012 | Land Evidence Date |