Action Date | Action Description |
---|---|
Jan 17, 2013 | Assent Application Received |
Jan 18, 2013 | Administrative Review for Completeness |
Jan 28, 2013 | Team Review for Completeness |
Jan 28, 2013 | Deficient Application - Owner Notification Sent |
Feb 14, 2013 | Deficient Application Picked Up |
Mar 04, 2013 | Deficiency Response Received |
Mar 06, 2013 | Team Review for Completeness |
Mar 06, 2013 | Application Accepted |
Mar 20, 2013 | Biologist Report |
Mar 21, 2013 | HPHC Historical Preservation No Effect |
Mar 25, 2013 | Permit Approved |
Mar 25, 2013 | Typist for Processing |
Mar 25, 2013 | Executive Sign Off |
Mar 25, 2013 | Sent to Photo Copy |
Jul 26, 2013 | Land Evidence Date |
Sep 25, 2013 | Letter of Authorization |
Jan 03, 2019 | Monitoring Report |