Action Date | Action Description |
---|---|
Feb 04, 2013 | Assent Application Received |
Feb 04, 2013 | Administrative Review for Completeness |
Feb 05, 2013 | Team Review for Completeness |
Feb 05, 2013 | Application Accepted |
Mar 25, 2013 | US Army Corp of Engineers Permit Date |
Apr 05, 2013 | HPHC Historical Preservation No Effect |
Apr 29, 2013 | Additional Information Received |
May 02, 2013 | Biologist Report |
May 04, 2013 | Commencement of Work Notice received |
May 04, 2013 | Correspondence Received |
May 06, 2013 | Permit Approved |
May 06, 2013 | Typist for Processing |
May 07, 2013 | Executive Sign Off |
May 07, 2013 | Sent to Photo Copy |
May 08, 2013 | Land Evidence Date |
May 13, 2013 | Water Quality Certification |