Action Date | Action Description |
---|---|
Mar 14, 2013 | Assent Application Received |
Mar 15, 2013 | Administrative Review for Completeness |
Mar 19, 2013 | Team Review for Completeness |
Mar 19, 2013 | Application Accepted |
Apr 01, 2013 | HPHC Historical Preservation No Effect |
May 20, 2013 | Additional Information Received |
Feb 21, 2014 | Additional Information Received |
Jul 09, 2014 | Plans Received |
Jul 21, 2014 | Plans Received |
Sep 15, 2014 | Correspondence Received |
Sep 17, 2014 | Biologist Report |
Oct 02, 2014 | Permit Approved |
Oct 03, 2014 | Typist for Processing |
Oct 03, 2014 | Executive Sign Off |
Oct 03, 2014 | Sent to Photo Copy |
Nov 07, 2014 | US Army Corps of Engineers Approval Received |
Sep 30, 2016 | Monitoring Report |
Nov 18, 2016 | Commencement of Work Notice received |
Dec 05, 2016 | Monitoring Report |
Mar 03, 2017 | Monitoring Report |
Jun 05, 2017 | Monitoring Report |
Oct 25, 2017 | Monitoring Report |
Jun 01, 2018 | Expiration of Assent/End of Tolling Legislation |
Jun 22, 2018 | Monitoring Report |
Feb 22, 2019 | Monitoring Report |
Sep 16, 2020 | Monitoring Report |
Jul 07, 2021 | Monitoring Report |
Nov 17, 2022 | Monitoring Report |