Action Date Action Description
Mar 28, 2013 Assent Application Received
Mar 29, 2013 Administrative Review for Completeness
Apr 02, 2013 Team Review for Completeness
Apr 02, 2013 Team Review for Completeness
Apr 02, 2013 Application Accepted
Apr 02, 2013 Category B assigned
Apr 10, 2013 30 day Public Notice Issued
Apr 16, 2013 Public Hearing Notices Mailed
May 06, 2013 HPHC Historical Preservation No Effect
May 10, 2013 Correspondence Received
May 10, 2013 Public Notice End Date
May 20, 2013 Biologist Report
May 20, 2013 Engineering Report
May 28, 2013 Semi-Monthly Meeting Date Scheduled
May 28, 2013 Water Quality Certification
May 28, 2013 Council Approval Granted
May 28, 2013 Semi-Monthly Meeting Held
Jun 10, 2013 Stipulation Package by Engineer
Jun 25, 2013 Legal Response/Decision
Jun 25, 2013 Under Review/Decision
Jun 25, 2013 30 Day Appeal Notification to Owner
Jun 26, 2013 Stipulation Package from Biologist
Jul 17, 2013 Typist for Processing
Jul 17, 2013 Executive Sign Off
Jul 17, 2013 Sent to Photo Copy
Jul 17, 2013 Permit Approved
Aug 01, 2013 Modification Request
Aug 06, 2013 Engineering Report
Aug 06, 2013 Biologist Report
Aug 06, 2013 Engineering Report
Aug 07, 2013 Typist for Processing
Aug 07, 2013 Modification Approved
Aug 08, 2013 Executive Sign Off
Aug 08, 2013 Sent to Photo Copy
Aug 19, 2013 Water Quality Certification
Oct 07, 2013 US Army Corps of Engineers Approval Received

Details:

File No
2013-03-216
Town
Portsmouth
First Name
Department of Environmental Ma
Last Name
Street
Route 24 Gull Cove Boat Ramp
Location
Route 24 Gull Cove Boat Ramp
Plat/Map
8
Lot/Block
3
Decision Date
Jul 17, 2013
Dock Reg.No
Project
repair existing boat ramp & access road @ Gull Cove Boat ramp
Description
Docks, Piers, Floats (Non-Residential)
Water Area
Sakonnet River
Easement
0
Acceptance Date
Apr 02, 2013

Back to List