Action Date | Action Description |
---|---|
Mar 28, 2013 | Assent Application Received |
Mar 29, 2013 | Administrative Review for Completeness |
Apr 02, 2013 | Team Review for Completeness |
Apr 02, 2013 | Team Review for Completeness |
Apr 02, 2013 | Application Accepted |
Apr 02, 2013 | Category B assigned |
Apr 10, 2013 | 30 day Public Notice Issued |
Apr 16, 2013 | Public Hearing Notices Mailed |
May 06, 2013 | HPHC Historical Preservation No Effect |
May 10, 2013 | Correspondence Received |
May 10, 2013 | Public Notice End Date |
May 20, 2013 | Biologist Report |
May 20, 2013 | Engineering Report |
May 28, 2013 | Semi-Monthly Meeting Date Scheduled |
May 28, 2013 | Water Quality Certification |
May 28, 2013 | Council Approval Granted |
May 28, 2013 | Semi-Monthly Meeting Held |
Jun 10, 2013 | Stipulation Package by Engineer |
Jun 25, 2013 | Legal Response/Decision |
Jun 25, 2013 | Under Review/Decision |
Jun 25, 2013 | 30 Day Appeal Notification to Owner |
Jun 26, 2013 | Stipulation Package from Biologist |
Jul 17, 2013 | Typist for Processing |
Jul 17, 2013 | Executive Sign Off |
Jul 17, 2013 | Sent to Photo Copy |
Jul 17, 2013 | Permit Approved |
Aug 01, 2013 | Modification Request |
Aug 06, 2013 | Engineering Report |
Aug 06, 2013 | Biologist Report |
Aug 06, 2013 | Engineering Report |
Aug 07, 2013 | Typist for Processing |
Aug 07, 2013 | Modification Approved |
Aug 08, 2013 | Executive Sign Off |
Aug 08, 2013 | Sent to Photo Copy |
Aug 19, 2013 | Water Quality Certification |
Oct 07, 2013 | US Army Corps of Engineers Approval Received |