Action Date | Action Description |
---|---|
Apr 04, 2013 | Assent Application Received |
Apr 07, 2013 | Administrative Review for Completeness |
May 06, 2013 | Deficient Application - Owner Notification Sent |
May 17, 2013 | Deficiency Response Received |
Jun 06, 2013 | Team Review for Completeness |
Jun 06, 2013 | Team Review for Completeness |
Jun 06, 2013 | Application Accepted |
Jun 11, 2013 | 30 day Public Notice Issued |
Jul 01, 2013 | Plans Received |
Jul 09, 2013 | Objections/Comments Received |
Jul 11, 2013 | Public Notice End Date |
Jul 22, 2013 | HPHC Historical Preservation No Effect |
Dec 19, 2013 | 30-Day Notification of Cancellation letter |
Dec 20, 2013 | Certified Receipt Received |
Jan 16, 2014 | Additional Information Received |
Jan 28, 2014 | Plans Received |
Jan 28, 2014 | Biologist Report |
Jan 31, 2014 | Supervisor Biologist SignOff |
Jan 31, 2014 | Supervisor Engineer SignOff |
Jan 31, 2014 | Executive Signoff of Staff Reports |
Feb 18, 2014 | Mail Agenda Notice |
Feb 24, 2014 | US Army Corps of Engineers Approval Received |
Feb 25, 2014 | Council Approval Granted |
Feb 25, 2014 | Semi-Monthly Meeting Held |
Feb 25, 2014 | Semi-Monthly Meeting Date Scheduled |
Feb 26, 2014 | Stipulation Package from Biologist |
Mar 10, 2014 | Legal Response/Decision |
Mar 10, 2014 | 30 Day Appeal Notification to Owner |
Mar 12, 2014 | Typist for Processing |
Mar 12, 2014 | Permit Approved |
Mar 13, 2014 | Executive Sign Off |
Mar 13, 2014 | Sent to Photo Copy |
May 02, 2014 | Land Evidence Date |