Action Date | Action Description |
---|---|
Apr 04, 2013 | Assent Application Received |
Apr 05, 2013 | Administrative Review for Completeness |
Apr 05, 2013 | Team Review for Completeness |
Apr 05, 2013 | Team Review for Completeness |
Apr 05, 2013 | Application Accepted |
May 06, 2013 | HPHC Historical Preservation No Effect |
Jun 13, 2013 | Additional Information Received |
Jun 25, 2013 | Water Quality Certification |
Jul 18, 2013 | Biologist Report |
Jul 18, 2013 | Engineering Report |
Jul 25, 2013 | Typist for Processing |
Jul 29, 2013 | Executive Sign Off |
Jul 29, 2013 | Sent to Photo Copy |
Aug 05, 2013 | Permit Approved |
Aug 23, 2013 | Land Evidence Date |
Aug 23, 2013 | Land Evidence Date |
Aug 29, 2013 | Conservation Easement Recording received |