Action Date | Action Description |
---|---|
Administrative Review for Completeness | |
HPHC Historical Preservation No Effect | |
Jun 04, 2013 | Assent Application Received |
Jun 05, 2013 | Administrative Review for Completeness |
Jul 19, 2013 | Team Review for Completeness |
Jul 19, 2013 | Team Review for Completeness |
Jul 19, 2013 | Additional Information Received |
Jul 23, 2013 | Application Accepted |
Jul 23, 2013 | Biologist Report |
Jul 23, 2013 | Plans Received |
Jul 23, 2013 | 30 day Public Notice Issued |
Aug 14, 2013 | HPHC Historical Preservation No Effect |
Aug 23, 2013 | Public Notice End Date |
Sep 25, 2013 | Plans Received |
Sep 27, 2013 | Additional Information Received |
Oct 09, 2013 | Public Hearing Notices Mailed |
Oct 18, 2013 | Stipulation Package from Biologist |
Nov 12, 2013 | Council Approval Granted |
Nov 12, 2013 | Semi-Monthly Meeting Date Scheduled |
Nov 12, 2013 | Public Hearing Scheduled |
Nov 12, 2013 | Semi-Monthly Meeting Held |
Nov 19, 2013 | 30 Day Appeal Notification to Owner |
Nov 19, 2013 | Legal Response/Decision |
Nov 21, 2013 | US Army Corps of Engineers Approval Received |
Dec 04, 2013 | Typist for Processing |
Dec 04, 2013 | Permit Approved |
Dec 05, 2013 | Executive Sign Off |
Dec 05, 2013 | Sent to Photo Copy |
Dec 09, 2013 | Land Evidence Date |
Mar 14, 2016 | Modification Request |