Action Date | Action Description |
---|---|
Jun 17, 2013 | Freshwater Wetland - Preliminary Determination |
Jun 17, 2013 | Administrative Review for Completeness |
Jun 21, 2013 | Team Review for Completeness |
Jul 23, 2013 | Application Accepted |
Jul 23, 2013 | Team Review for Completeness |
Sep 03, 2013 | Historical Preservation Conditional Approval |
Sep 13, 2013 | Correspondence Received |
Sep 27, 2013 | Biologist Report |
Sep 27, 2013 | Engineering Report |
Sep 30, 2013 | Typist for Processing |
Sep 30, 2013 | Executive Sign Off |
Sep 30, 2013 | Sent to Photo Copy |
Sep 30, 2013 | Permit Approved |
Oct 08, 2013 | Land Evidence Date |
Oct 24, 2014 | Modification Request |
Oct 27, 2014 | Administrative Review for Completeness |
Jan 19, 2015 | Team Review for Completeness |
Jan 19, 2015 | Team Review for Completeness |
Jan 20, 2015 | Typist for Processing |
Jan 20, 2015 | Modification Approved |
Jan 23, 2015 | Executive Sign Off |
Jan 23, 2015 | Sent to Photo Copy |
Apr 28, 2016 | Land Evidence Date |