Action Date Action Description
Jun 18, 2013 Assent Application Received
Jun 19, 2013 Administrative Review for Completeness
Jul 08, 2013 Team Review for Completeness
Jul 08, 2013 Team Review for Completeness
Jul 08, 2013 Application Accepted
Jul 09, 2013 30 day Public Notice Issued
Jul 22, 2013 Objections/Comments Received
Jul 23, 2013 Historical Preservation Conditional Approval
Jul 24, 2013 Public Notice End Date
Aug 02, 2013 Additional Information Received
Aug 08, 2013 Interim Approval Granted
Aug 09, 2013 Additional Information Received
Apr 10, 2014 Correspondence Received
Feb 18, 2015 Plans Received
May 20, 2015 Correspondence Received
Jun 19, 2015 Correspondence Received
Jul 02, 2015 Plans Received
Aug 03, 2015 Interim Approval Granted
Sep 03, 2015 Water Quality Certification
Sep 18, 2015 Engineering Report
Sep 18, 2015 Additional Information Requested from Applicant
Sep 21, 2015 Correspondence Received
Oct 13, 2015 Correspondence Received
Oct 27, 2015 HPHC Historical Preservation No Effect
Nov 05, 2015 Plans Received
Nov 18, 2015 Additional Information Received
Nov 19, 2015 Biologist Report
Nov 20, 2015 Typist for Processing
Nov 20, 2015 Executive Sign Off
Nov 20, 2015 Sent to Photo Copy
Nov 20, 2015 Permit Approved
Nov 24, 2015 Additional Information Received
Mar 14, 2016 Modification Request
Mar 16, 2016 Administrative Review for Completeness
Mar 17, 2016 Team Review for Completeness
Mar 17, 2016 Team Review for Completeness
Mar 30, 2016 HPHC Historical Preservation No Effect
Mar 31, 2016 Additional Information Received
Apr 15, 2016 Modification Request
Apr 15, 2016 Plans Received
Apr 18, 2016 Administrative Review for Completeness
Apr 22, 2016 Plans Received
Apr 27, 2016 Modification Withdrawn
May 16, 2016 Typist for Processing
May 16, 2016 Executive Sign Off
May 16, 2016 Sent to Photo Copy
May 16, 2016 Modification Approved
May 16, 2016 Biologist Report
May 16, 2016 Engineering Report
May 20, 2016 Additional Information Received
Jun 19, 2018 Correspondence Received
May 20, 2019 Correspondence Received
Jun 19, 2019 Modification Request
Jun 21, 2019 Administrative Review for Completeness
Jul 19, 2019 Team Review for Completeness
Jul 19, 2019 Application Accepted
Aug 19, 2019 Additional Information Received
Aug 22, 2019 HPHC Review Pending
Aug 22, 2019 HPHC Historical Preservation No Effect
Sep 17, 2019 Additional Information Received
Sep 20, 2019 Additional Information Received
Sep 30, 2019 Additional Information Received
Oct 04, 2019 Additional Information Received
Oct 04, 2019 Extension of Permit Request
Oct 09, 2019 Additional Information Received
Oct 11, 2019 Biologist Report
Oct 15, 2019 Typist for Processing
Oct 15, 2019 Executive Sign Off
Oct 15, 2019 Modification Approved
Oct 15, 2019 Extension Approved
Nov 08, 2019 Correspondence Received
Jan 10, 2020 Extension of Permit Request
Jan 24, 2020 Enforcement Compliance Inspection Required
Jan 24, 2020 Process Extension
Jan 24, 2020 Extension Approved
Oct 06, 2020 Modification Request
Oct 06, 2020 Administrative Review for Completeness
Oct 07, 2020 Project Manager
Nov 19, 2020 Policy Review
Nov 19, 2020 Modification Approved
Dec 11, 2020 Land Evidence Date
Dec 16, 2020 Land Evidence Date
Jun 21, 2021 Extension of Permit Request
Mar 17, 2022 Enforcement Compliance Inspection Required
Mar 25, 2022 Extension Approved

Details:

File No
2013-06-080
Town
East Providence
First Name
LLC & Kettle Point, LLC
Last Name
Long Rock Cove
Street
Kettle Point Avenue
Location
Kettle Point Avenue
Plat/Map
108|109|209
Lot/Block
1,2|1,2,3|1,4
Decision Date
Nov 20, 2015
Dock Reg.No
Project
Develop a 407 residential rental & condos,roadway,parking,utilities @Kettle Point
Description
Subdivision (Sewered)
Water Area
Easement
0
Acceptance Date
Jul 19, 2019

Back to List