Action Date | Action Description |
---|---|
Nov 06, 2013 | Assent Application Received |
Nov 06, 2013 | Administrative Review for Completeness |
Nov 15, 2013 | Team Review for Completeness |
Nov 15, 2013 | Application Accepted |
Nov 29, 2013 | Biologist Report |
Dec 03, 2013 | Typist for Processing |
Dec 03, 2013 | Executive Sign Off |
Dec 03, 2013 | Sent to Photo Copy |
Dec 03, 2013 | Permit Approved |
Dec 10, 2013 | Land Evidence Date |
Dec 18, 2013 | HPHC Historical Preservation No Effect |
Jun 18, 2014 | Modification Request |
Jun 18, 2014 | Administrative Review for Completeness |
Jun 19, 2014 | Team Review for Completeness |
Jul 01, 2014 | Biologist Report |
Jul 02, 2014 | Typist for Processing |
Jul 02, 2014 | Executive Sign Off |
Jul 02, 2014 | Sent to Photo Copy |
Jul 02, 2014 | Modification Approved |
Jul 07, 2014 | Land Evidence Date |
Jul 30, 2014 | HPHC Historical Preservation No Effect |