Action Date | Action Description |
---|---|
Jan 13, 2014 | Assent Application Received |
Jan 13, 2014 | Administrative Review for Completeness |
Jan 27, 2014 | Team Review for Completeness |
Jan 27, 2014 | Application Accepted |
Jan 31, 2014 | Engineering Report |
Feb 03, 2014 | Plans Received |
Feb 05, 2014 | Permit Approved |
Feb 05, 2014 | Typist for Processing |
Feb 06, 2014 | Executive Sign Off |
Feb 06, 2014 | Sent to Photo Copy |
Feb 11, 2014 | Land Evidence Date |
Feb 21, 2014 | HPHC Historical Preservation No Effect |