Action Date | Action Description |
---|---|
Jan 15, 2014 | Assent Application Received |
Jan 15, 2014 | Administrative Review for Completeness |
Jan 23, 2014 | Team Review for Completeness |
Jan 23, 2014 | Application Accepted |
Feb 04, 2014 | HPHC Historical Preservation No Effect |
Feb 12, 2014 | 30 day Public Notice Issued |
Mar 12, 2014 | Public Notice End Date |
Mar 13, 2014 | Category A* (Docks) |
Mar 19, 2014 | Biologist Report |
Mar 21, 2014 | Typist for Processing |
Mar 21, 2014 | Permit Approved |
Mar 24, 2014 | Executive Sign Off |
Mar 24, 2014 | Sent to Photo Copy |
Apr 04, 2014 | Land Evidence Date |
Apr 11, 2014 | US Army Corps of Engineers Approval Received |