Action Date | Action Description |
---|---|
Jan 23, 2014 | Assent Application Received |
Jan 24, 2014 | Administrative Review for Completeness |
Jan 27, 2014 | Team Review for Completeness |
Jan 27, 2014 | Application Accepted |
Jan 28, 2014 | Engineering Report |
Jan 29, 2014 | Executive Signoff of Staff Reports |
Jan 30, 2014 | Ready to Schedule Semi-Monthly Meeting |
Jan 30, 2014 | Mail Agenda Notice |
Feb 11, 2014 | Council Approval Granted |
Feb 11, 2014 | Semi-Monthly Meeting Date Scheduled |
Feb 11, 2014 | Semi-Monthly Meeting Held |
Feb 26, 2014 | Typist for Processing |
Feb 26, 2014 | Permit Approved |
Mar 03, 2014 | Under Review/Decision |
Mar 03, 2014 | Stipulation Package by Engineer |
Mar 03, 2014 | Legal Response/Decision |
Mar 10, 2014 | 30 Day Appeal Notification to Owner |
Mar 10, 2014 | Executive Sign Off |
Mar 10, 2014 | Sent to Photo Copy |
Mar 24, 2014 | Land Evidence Date |