Action Date | Action Description |
---|---|
Mar 06, 2014 | Assent Application Received |
Mar 07, 2014 | Administrative Review for Completeness |
Mar 12, 2014 | Team Review for Completeness |
Mar 12, 2014 | Application Accepted |
Apr 09, 2014 | 30 day Public Notice Issued |
Apr 11, 2014 | HPHC Historical Preservation No Effect |
Jun 06, 2014 | Objections/Comments Received |
Aug 13, 2014 | Plans Received |
Aug 14, 2014 | Biologist Report |
Aug 14, 2014 | Engineering Report |
Aug 15, 2014 | Typist for Processing |
Aug 15, 2014 | Executive Sign Off |
Aug 15, 2014 | Sent to Photo Copy |
Aug 15, 2014 | Permit Approved |
Aug 22, 2014 | Land Evidence Date |