Action Date | Action Description |
---|---|
Aug 04, 2014 | Assent Application Received |
Aug 05, 2014 | Administrative Review for Completeness |
Aug 12, 2014 | Team Review for Completeness |
Aug 12, 2014 | Deficient Application - Owner Notification Sent |
Aug 13, 2014 | HPHC Historical Preservation No Effect |
Aug 20, 2014 | Plans Received |
Sep 02, 2014 | Deficient Application Picked Up |
Oct 15, 2014 | Deficiency Response Received |
Oct 24, 2014 | Team Review for Completeness |
Oct 24, 2014 | Application Accepted |
Nov 25, 2014 | 30 day Public Notice Issued |
Dec 26, 2014 | Public Notice End Date |
Dec 31, 2014 | Biologist Report |
Jan 12, 2015 | Typist for Processing |
Jan 12, 2015 | Permit Approved |
Jan 14, 2015 | Executive Sign Off |
Jan 14, 2015 | Sent to Photo Copy |
Jan 20, 2015 | Land Evidence Date |
Jan 30, 2015 | US Army Corps of Engineers Approval Received |
Feb 20, 2015 | Enforcement Review of application for compliance |
Feb 20, 2015 | Correspondence Mailed/Faxed/E-mailed |