Action Date | Action Description |
---|---|
Oct 20, 2015 | Administrative Review for Completeness |
Oct 22, 2015 | Team Review for Completeness |
Oct 22, 2015 | Team Review for Completeness |
Oct 22, 2015 | Additional Information Received |
Oct 22, 2015 | Application Accepted |
Oct 22, 2015 | Category B assigned |
Nov 30, 2015 | Additional Information Requested from Applicant |
Nov 30, 2015 | HPHC Historical Preservation No Effect |
Mar 11, 2016 | Plans Received |
Jun 09, 2016 | Plans Received |
Jul 07, 2016 | 30 day Public Notice Issued |
Aug 07, 2016 | Public Notice End Date |
Sep 07, 2016 | Plans Received |
Oct 07, 2016 | Water Quality Certification |
Dec 19, 2016 | Dock/1.1.6 Review approval |
Feb 21, 2017 | Biologist Report |
Feb 24, 2017 | Engineering Report |
Feb 24, 2017 | Typist for Processing |
Feb 24, 2017 | Executive Sign Off |
Feb 24, 2017 | Sent to Photo Copy |
Feb 24, 2017 | Permit Approved |
Mar 27, 2017 | Land Evidence Date |
May 01, 2017 | Correspondence Received |
May 19, 2017 | Additional Information Received |
May 22, 2017 | Additional Information Received |
May 27, 2017 | Land Evidence Date |