Action Date | Action Description |
---|---|
Oct 19, 2015 | Freshwater Wetland - Preliminary Determination |
Oct 20, 2015 | Administrative Review for Completeness |
Nov 30, 2015 | Team Review for Completeness |
Nov 30, 2015 | HPHC Historical Preservation No Effect |
Nov 30, 2015 | Application Accepted |
Dec 01, 2015 | Biologist Report |
Dec 10, 2015 | HPHC Historical Preservation No Effect |
Feb 02, 2016 | Typist for Processing |
Feb 05, 2016 | Executive Sign Off |
Feb 05, 2016 | Sent to Photo Copy |
Feb 05, 2016 | Permit Approved |
Feb 29, 2016 | Land Evidence Date |
Jul 22, 2016 | Modification Request |
Jul 25, 2016 | Administrative Review for Completeness |
Jul 28, 2016 | Team Review for Completeness |
Jul 28, 2016 | Application Accepted |
Aug 17, 2016 | HPHC Historical Preservation No Effect |
Sep 02, 2016 | Biologist Report |
Sep 02, 2016 | Typist for Processing |
Sep 07, 2016 | Executive Sign Off |
Sep 07, 2016 | Sent to Photo Copy |
Sep 12, 2016 | Modification Approved |
Sep 19, 2017 | Land Evidence Date |