Action Date | Action Description |
---|---|
Dec 22, 2015 | Assent Application Received |
Dec 22, 2015 | Administrative Review for Completeness |
Dec 22, 2015 | Team Review for Completeness |
Dec 22, 2015 | Application Accepted |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Apr 01, 2016 | Additional Information Requested from Applicant |
May 05, 2016 | Plans Received |
Jun 28, 2016 | Plans Received |
Jul 11, 2016 | Additional Information Received |
Aug 17, 2016 | Plans Received |
Aug 24, 2016 | Plans Received |
Aug 25, 2016 | Biologist Report |
Oct 03, 2016 | Biologist Report |
Oct 11, 2016 | Typist for Processing |
Oct 12, 2016 | Executive Sign Off |
Oct 12, 2016 | Sent to Photo Copy |
Oct 12, 2016 | Permit Approved |
Nov 01, 2016 | Land Evidence Date |
Feb 06, 2019 | Modification Request |
Feb 06, 2019 | Administrative Review for Completeness |
Feb 12, 2019 | Plans Received |
Feb 22, 2019 | Application Accepted |
Feb 22, 2019 | Team Review for Completeness |
Mar 13, 2019 | HPHC Historical Preservation No Effect |
Mar 13, 2019 | HPHC Review Pending |
Mar 21, 2019 | Biologist Report |
Mar 25, 2019 | Modification Approved |
Mar 25, 2019 | Permit Approved |
Mar 25, 2019 | Typist for Processing |
Mar 25, 2019 | Executive Sign Off |
Mar 25, 2019 | Sent to Photo Copy |
Apr 04, 2019 | Land Evidence Date |