Action Date | Action Description |
---|---|
Mar 17, 2016 | Assent Application Received |
Mar 17, 2016 | Administrative Review for Completeness |
Mar 21, 2016 | Team Review for Completeness |
Mar 21, 2016 | Deficient Application - Owner Notification Sent |
Apr 01, 2016 | Deficient Application Picked Up |
May 10, 2016 | Deficiency Response Received |
May 11, 2016 | Team Review for Completeness |
May 11, 2016 | Application Accepted |
May 23, 2016 | HPHC Historical Preservation No Effect |
Jun 10, 2016 | Plans Received |
Jun 21, 2016 | 30 day Public Notice Issued |
Jul 21, 2016 | Public Notice End Date |
Aug 16, 2016 | Biologist Report |
Aug 17, 2016 | Category A* (Docks) |
Aug 17, 2016 | Typist for Processing |
Aug 19, 2016 | Executive Sign Off |
Aug 19, 2016 | Sent to Photo Copy |
Aug 19, 2016 | Permit Approved |
Aug 25, 2016 | US Army Corps of Engineers Approval Received |
Sep 20, 2016 | Land Evidence Date |