Action Date | Action Description |
---|---|
Monitoring Report | |
Monitoring Report | |
Mar 17, 2016 | Assent Application Received |
Mar 28, 2016 | Deficient Application Picked Up |
May 19, 2016 | Deficiency Response Received |
Aug 12, 2016 | Correspondence Received |
Aug 18, 2016 | Deficient Application - Owner Notification Sent |
Aug 18, 2016 | Team Review for Completeness |
Sep 14, 2016 | Deficient Application Picked Up |
Nov 20, 2018 | Deficiency Response Received |
Feb 28, 2019 | Team Review for Completeness |
Mar 01, 2019 | Application Accepted |
Apr 24, 2019 | Biologist Report |
Apr 25, 2019 | Typist for Processing |
Apr 25, 2019 | Executive Sign Off |
Apr 25, 2019 | Sent to Photo Copy |
Apr 25, 2019 | Permit Approved |
Jul 31, 2019 | Land Evidence Date |
Aug 17, 2021 | Monitoring Report |
Dec 01, 2021 | Monitoring Report |
Apr 22, 2022 | Extension of Permit Request |
Apr 28, 2022 | Enforcement Compliance Inspection Required |
Apr 28, 2022 | Process Extension |
Apr 28, 2022 | Executive Sign Off |
Apr 28, 2022 | Extension Approved |
Mar 01, 2023 | Monitoring Report |
May 22, 2024 | Monitoring Report |
Sep 17, 2024 | Assent Requirement |