Action Date | Action Description |
---|---|
Jun 29, 2016 | Assent Application Received |
Jun 30, 2016 | Administrative Review for Completeness |
Jun 30, 2016 | Team Review for Completeness |
Jun 30, 2016 | Application Accepted |
Jul 07, 2016 | 30 day Public Notice Issued |
Jul 19, 2016 | HPHC Historical Preservation No Effect |
Aug 05, 2016 | Objections/Comments Received |
Aug 07, 2016 | Public Notice End Date |
Aug 09, 2016 | Comments Received |
Aug 24, 2016 | Note to File |
Sep 12, 2016 | Correspondence Received |
Sep 15, 2016 | Plans Received |
Sep 15, 2016 | US Army Corps of Engineers Approval Received |
Sep 26, 2016 | Mail Agenda Notice |
Sep 29, 2016 | Additional Information Received |
Sep 29, 2016 | Biologist Report |
Sep 30, 2016 | Supervisor Biologist SignOff |
Oct 03, 2016 | Supervisor Engineer SignOff |
Oct 04, 2016 | Executive Signoff of Staff Reports |
Oct 11, 2016 | Semi-Monthly Meeting Date Scheduled |
Dec 16, 2016 | 30 Day Appeal Notification to Owner |
Dec 16, 2016 | Legal Response/Decision |
Feb 24, 2017 | Stipulation Package from Biologist |
Feb 27, 2017 | Typist for Processing |
Feb 27, 2017 | Executive Sign Off |
Feb 27, 2017 | Sent to Photo Copy |
Feb 27, 2017 | Permit Approved |
Mar 20, 2017 | Assent Correction Mailed |
Mar 28, 2017 | Land Evidence Date |
May 31, 2017 | Commencement of Work Notice received |
Aug 16, 2017 | Enforcement Review of application for compliance |
Sep 28, 2017 | Additional Information Received |