Action Date | Action Description |
---|---|
Nov 09, 2017 | Dredge Application |
Nov 09, 2017 | Administrative Review for Completeness |
Nov 20, 2017 | Team Review for Completeness |
Nov 20, 2017 | Application Accepted |
Nov 22, 2017 | Additional Information Received |
Dec 01, 2017 | 30 day Public Notice Issued |
Dec 14, 2017 | Letter of Support for Project |
Dec 31, 2017 | Public Notice End Date |
Jan 05, 2018 | Typist for Processing |
Jan 05, 2018 | Executive Sign Off |
Jan 05, 2018 | Permit Approved |
Jan 05, 2018 | Engineering Report |
Jan 10, 2018 | Land Evidence Date |