Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Mar 16, 2018 | Assent Application Received |
Mar 16, 2018 | Administrative Review for Completeness |
Mar 30, 2018 | Team Review for Completeness |
Mar 30, 2018 | Application Accepted |
Apr 02, 2018 | Category A* (Docks) |
Apr 05, 2018 | 30 day Public Notice Issued |
Apr 11, 2018 | HPHC Historical Preservation No Effect |
May 05, 2018 | Public Notice End Date |
May 22, 2018 | Dock/1.1.6 Review approval |
Jun 04, 2018 | Plans Received |
Jun 11, 2018 | Typist for Processing |
Jun 11, 2018 | Executive Sign Off |
Jun 11, 2018 | Sent to Photo Copy |
Jun 11, 2018 | Permit Approved |
Jun 11, 2018 | Biologist Report |
Jun 22, 2018 | Land Evidence Date |
May 21, 2021 | Extension of Permit Request |
Feb 11, 2022 | Enforcement Compliance Inspection Required |
Feb 15, 2022 | Process Extension |
Feb 15, 2022 | Extension Approved |