Action Date | Action Description |
---|---|
Apr 11, 2018 | Assent Application Received |
Apr 12, 2018 | Administrative Review for Completeness |
Apr 19, 2018 | Team Review for Completeness |
Apr 23, 2018 | Deficient Application - Owner Notification Sent |
Apr 23, 2018 | Team Review for Completeness |
May 10, 2018 | Deficient Application Picked Up |
Jun 04, 2018 | Deficiency Response Received |
Jun 05, 2018 | Team Review for Completeness |
Jun 06, 2018 | Team Review for Completeness |
Jun 06, 2018 | Application Accepted |
Jun 06, 2018 | Category B assigned |
Jun 19, 2018 | 30 day Public Notice Issued |
Jun 26, 2018 | HPHC Historical Preservation No Effect |
Jul 19, 2018 | Public Notice End Date |
Sep 21, 2018 | Engineering Report |
Sep 24, 2018 | Typist for Processing |
Sep 24, 2018 | Executive Sign Off |
Sep 24, 2018 | Sent to Photo Copy |
Sep 24, 2018 | Permit Approved |
Oct 10, 2018 | Land Evidence Date |