Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Apr 23, 2018 | Assent Application Received |
Apr 23, 2018 | Administrative Review for Completeness |
Apr 25, 2018 | Team Review for Completeness |
Apr 25, 2018 | Application Accepted |
Apr 25, 2018 | Category A* (Docks) |
May 04, 2018 | 30 day Public Notice Issued |
May 11, 2018 | HPHC Historical Preservation No Effect |
May 22, 2018 | Dock/1.1.6 Review approval |
Jun 04, 2018 | Public Notice End Date |
Jun 05, 2018 | Biologist Report |
Jun 06, 2018 | Typist for Processing |
Jun 06, 2018 | Executive Sign Off |
Jun 06, 2018 | Sent to Photo Copy |
Jun 06, 2018 | Permit Approved |
Jul 19, 2018 | US Army Corps of Engineers Approval Received |
Jan 24, 2019 | Land Evidence Date |
Sep 09, 2019 | Modification Request |
Sep 18, 2019 | Administrative Review for Completeness |
Sep 18, 2019 | Team Review for Completeness |
Sep 26, 2019 | Biologist Report |
Sep 26, 2019 | Modification Approved |
Oct 04, 2019 | Land Evidence Date |
Dec 16, 2019 | HPHC Historical Preservation No Effect |
Dec 16, 2019 | HPHC Review Pending |