Action Date | Action Description |
---|---|
Aug 08, 2018 | Assent Application Received |
Aug 08, 2018 | Administrative Review for Completeness |
Aug 24, 2018 | Team Review for Completeness |
Aug 24, 2018 | Application Accepted |
Sep 18, 2018 | HPHC Historical Preservation No Effect |
Oct 05, 2018 | Additional Information Requested from Applicant |
Nov 02, 2018 | Additional Information Requested from Applicant |
Dec 06, 2018 | Additional Information Received |
Jan 03, 2019 | Additional Information Requested from Applicant |
Jan 08, 2019 | Additional Information Received |
Jan 10, 2019 | Additional Information Received |
Feb 04, 2019 | Additional Information Requested from Applicant |
Feb 28, 2019 | Plans Received |
Sep 24, 2019 | Additional Information Requested from Applicant |
Oct 07, 2019 | Typist for Processing |
Oct 07, 2019 | Biologist Report |
Oct 08, 2019 | Permit Approved |
Oct 08, 2019 | Executive Sign Off |
Oct 08, 2019 | Sent to Photo Copy |
Oct 15, 2019 | Land Evidence Date |
May 25, 2021 | Conservation Easement Recording received |
Feb 28, 2022 | Additional Information Received |
Aug 01, 2022 | Additional Information Received |
Oct 06, 2022 | Additional Information Received |