Action Date | Action Description |
---|---|
Sep 20, 2018 | Assent Application Received |
Sep 21, 2018 | Administrative Review for Completeness |
Sep 21, 2018 | Team Review for Completeness |
Sep 21, 2018 | Additional Information Received |
Sep 21, 2018 | Application Accepted |
Oct 02, 2018 | HPHC Historical Preservation No Effect |
Feb 07, 2019 | Plans Received |
Apr 08, 2019 | Plans Received |
Apr 29, 2019 | Biologist Report |
Apr 30, 2019 | Typist for Processing |
Apr 30, 2019 | Executive Sign Off |
Apr 30, 2019 | Sent to Photo Copy |
Apr 30, 2019 | Permit Approved |
May 06, 2019 | Land Evidence Date |
May 28, 2019 | Commencement of Work Notice received |
Dec 02, 2019 | Monitoring Report |