Action Date Action Description
May 17, 2019 Assent Application Received
May 17, 2019 Administrative Review for Completeness
May 22, 2019 Team Review for Completeness
May 22, 2019 Application Accepted
Jun 24, 2019 HPHC Review Pending
Jun 24, 2019 HPHC Historical Preservation No Effect
Jul 23, 2019 Plans Received
Aug 23, 2019 Plans Received
Sep 20, 2019 Plans Received
Oct 28, 2019 Plans Received
Oct 29, 2019 Biologist Report
Oct 30, 2019 Permit Approved
Oct 30, 2019 Typist for Processing
Oct 31, 2019 Executive Sign Off
Oct 31, 2019 Sent to Photo Copy
Jan 09, 2020 Land Evidence Date
Jan 30, 2020 Modification Request
Jan 31, 2020 Administrative Review for Completeness
Feb 03, 2020 Bio Team Review for Completeness
Feb 18, 2020 Biologist Report
Feb 25, 2020 HPHC Historical Preservation No Effect
Feb 25, 2020 HPHC Review Pending
Feb 27, 2020 Modification Approved
Feb 27, 2020 Permit Approved
Mar 03, 2020 Land Evidence Date
Jul 07, 2021 Assent Requirement

Details:

File No
2019-05-068
Town
Barrington
First Name
Bay Spring Associates LLP
Last Name
Street
Sowams Road
Location
Sowams Road
Plat/Map
31
Lot/Block
325
Decision Date
Feb 27, 2020
Dock Reg.No
Project
c/m a residential dwelling;MOD SLC
Description
Dwelling, Sewered
Water Area
Palmer River
Easement
0
Acceptance Date
May 22, 2019