Action Date | Action Description |
---|---|
May 20, 2019 | Assent Application Received |
May 21, 2019 | Administrative Review for Completeness |
May 21, 2019 | Team Review for Completeness |
May 21, 2019 | Application Accepted |
Jun 03, 2019 | Biologist Report |
Jun 04, 2019 | Engineering Report |
Jun 04, 2019 | Category M assigned |
Jun 05, 2019 | Executive Sign Off |
Jun 05, 2019 | Sent to Photo Copy |
Jun 05, 2019 | Permit Approved |
Jun 05, 2019 | Typist for Processing |
Jun 24, 2019 | HPHC Historical Preservation No Effect |
Jun 24, 2019 | HPHC Review Pending |