Action Date | Action Description |
---|---|
May 30, 2019 | Assent Application Received |
May 30, 2019 | Administrative Review for Completeness |
Jun 04, 2019 | Team Review for Completeness |
Jun 04, 2019 | Application Accepted |
Jul 03, 2019 | HPHC Review Pending |
Jul 03, 2019 | HPHC Historical Preservation No Effect |
Jul 10, 2019 | Additional Information Requested from Applicant |
Jul 23, 2019 | Phone Call |
Jul 26, 2019 | Plans Received |
Aug 07, 2019 | Phone Call |
Aug 13, 2019 | Additional Information Received |
Aug 15, 2019 | Biologist Report |
Aug 20, 2019 | Typist for Processing |
Aug 20, 2019 | Executive Sign Off |
Aug 20, 2019 | Sent to Photo Copy |
Aug 20, 2019 | Permit Approved |
Aug 27, 2019 | Land Evidence Date |