Action Date | Action Description |
---|---|
Jun 26, 2019 | Assent Application Received |
Jun 26, 2019 | Administrative Review for Completeness |
Jul 03, 2019 | Team Review for Completeness |
Jul 03, 2019 | Deficient Application - Owner Notification Sent |
Jul 25, 2019 | Deficiency Response Received |
Jul 25, 2019 | Team Review for Completeness |
Jul 25, 2019 | Application Accepted |
Aug 28, 2019 | Biologist Report |
Sep 04, 2019 | HPHC Historical Preservation No Effect |
Sep 04, 2019 | Typist for Processing |
Sep 04, 2019 | Executive Sign Off |
Sep 04, 2019 | Sent to Photo Copy |
Sep 04, 2019 | Permit Approved |
Sep 09, 2019 | Land Evidence Date |