Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 26, 2019 | Assent Application Received |
Jun 26, 2019 | Administrative Review for Completeness |
Jul 08, 2019 | Team Review for Completeness |
Jul 08, 2019 | Application Accepted |
Jul 18, 2019 | 30 day Public Notice Issued |
Jul 24, 2019 | HPHC Review Pending |
Jul 24, 2019 | HPHC Historical Preservation No Effect |
Aug 18, 2019 | Public Notice End Date |
Sep 18, 2019 | 15 day Public Notice Issued |
Oct 03, 2019 | Public Notice End Date |
Oct 08, 2019 | Additional Information Received |
Nov 06, 2019 | Typist for Processing |
Nov 06, 2019 | Executive Sign Off |
Nov 06, 2019 | Sent to Photo Copy |
Nov 06, 2019 | Permit Approved |
Nov 06, 2019 | Engineering Report |
Nov 06, 2019 | Category A* (Docks) |
Nov 15, 2019 | US Army Corps of Engineers Approval Received |
Dec 06, 2019 | Land Evidence Date |
Nov 16, 2020 | Modification Request |
Nov 18, 2020 | Administrative Review for Completeness |
Dec 04, 2020 | Eng Team Review for Completeness |
Dec 04, 2020 | Project Manager |
Dec 18, 2020 | 30 day Public Notice Issued |
Dec 23, 2020 | HPHC Review Pending |
Dec 23, 2020 | HPHC Historical Preservation No Effect |
Jan 18, 2021 | Public Notice End Date |
Jan 19, 2021 | Comments Received |
Jan 21, 2021 | US Army Corps of Engineers Approval Received |
Mar 11, 2021 | Plans Received |
Apr 16, 2021 | Stipulation Package by Engineer |
Apr 16, 2021 | Engineering Report |
Apr 19, 2021 | Typist for Processing |
Apr 19, 2021 | Executive Sign Off |
Apr 19, 2021 | Sent to Photo Copy |
Apr 19, 2021 | Modification Approved |
May 03, 2021 | Land Evidence Date |