Action Date | Action Description |
---|---|
Jul 03, 2019 | Assent Application Received |
Jul 03, 2019 | Administrative Review for Completeness |
Jul 05, 2019 | Team Review for Completeness |
Jul 05, 2019 | Application Accepted |
Jul 29, 2019 | HPHC Review Pending |
Jul 29, 2019 | HPHC Historical Preservation No Effect |
Aug 20, 2019 | Additional Information Requested from Applicant |
Aug 22, 2019 | Biologist Report |
Aug 26, 2019 | Typist for Processing |
Aug 26, 2019 | Executive Sign Off |
Aug 26, 2019 | Sent to Photo Copy |
Aug 26, 2019 | Permit Approved |
Sep 03, 2019 | Land Evidence Date |